The company is advancing the construction of 50MW-class AI data centers in Ansan and Cheongna.

1 / 6

Details

  • KT Cloud is advancing efforts to secure 1GW-scale AI data center supply capacity by 2031.
  • The Ansan AI data center is planned at 50MW scale with a target completion in 2029, while the Cheongna AI data center is planned at 50MW-class scale with a target completion in Q1 2030.
  • In collaboration with Vertiv on next-generation AI data center technology, modular solutions will be applied to the Gunsan AI data center.
  • It introduced strategies for public DR, operational efficiency based on BIM and AIOps, and physical AI GPU infrastructure.