SoftBank Group Books ¥597.2 Billion Loss on AI Data Center Turbine Procurement

·2026.11.12 11:30

Key point

SoftBank Group disclosed a ¥597.2 billion loss from unrecoverable advance payments for gas turbines intended for AI data centers.

1 / 2

Details

  • SoftBank Group reported a ¥597.2 billion loss (approx. $3.7 billion) in its Q2 FY2027 results, stemming from revised procurement plans for power equipment for AI data centers.
  • The loss consists of ¥457 billion in nonrefundable advances and ¥140.2 billion in contract modification and settlement costs, following the cancellation of surplus turbine reservations.
  • SoftBank had made approximately $9.5 billion in advance payments via subsidiary Silver Bands 7 LLC; $6.6 billion remains allocated to the PORTS-Pike project in Ohio, while $2.9 billion was deemed unrecoverable.
  • The company secured rights to up to $2.1 billion in future equipment discounts but did not record them as assets due to uncertainty in purchase timing and value.
  • PORTS-Pike involves a 9.2 GW gas-fired power plant and an adjacent 8.0 GW data center leased to OpenAI, with construction scheduled to start in early 2027.
  • SoftBank CFO Yoshimitsu Goto denied Elon Musk's claim of a default on turbine orders, stating the loss resulted from changing business requirements rather than a contract breach.
  • Consolidated net loss for July–September 2026 was approximately ¥1.12 trillion, influenced by the equipment loss, Intel share valuation changes, and financing costs for $64.6 billion in OpenAI investments.