kt cloud interview: Six major changes in AI data centers by 2027 and on-site validation capabilities

KT CloudKT Cloud·Original
Operator Bae ChangHyun

Key point

kt cloud is preparing a roadmap for racks of up to 600kW and emphasized server-specific validation and pre-operation verification.

Details

  • In an interview, kt cloud DC Engineering Team Lead Ahn Gyeong-geun said that the competitiveness of AI data centers in 2027 will depend not on adopting the latest technologies, but on power and cooling designs tailored to customer servers and the ability to validate actual operations
  • Rack power is trending upward from around 10kW in existing customer environments to kt cloud’s current support level of 132~140kW, with a roadmap for next-generation GPU support reaching up to 600kW. The roadmap includes liquid cooling and 400~800V DC power distribution, and targets a PUE of 1.1 for next-generation designs
  • Validation is underway at different sites: a PoC at Yongsan Data Center, 13 technologies for next-generation GPU support at Mokdong AI Innovation Center, and liquid-cooling operations at Gasan Data Center colocation
  • Around 15~20 items are validated for each project, and the liquid-cooling commissioning test script is about 263 pages long. The scope of validation includes cooling performance and controls, incident response, and operational quality

Liquid Cooling and Pre-operation Validation

  • Power and cooling are designed at the pod level to maintain the temperature, flow rate, and pressure of coolant all the way to servers at the end of approximately 70~80m of piping
  • In 2023, when it was difficult to find suitable testing equipment on the market, kt cloud developed its own load bank to replicate server heat output and flow and pressure conditions. CFD analysis took around 48 hours per run, and the equipment was patented
  • At Gasan AI Data Center, which opened in November 2025, the valves and locking devices required for operation were incorporated at the design stage, allowing customer requests to be handled without additional construction. Commissioning is carried out in five stages, from L1 to L5

Power Availability and Construction Methods

  • Team Lead Ahn forecast that existing power supply methods would be sufficient through the Vera Rubin generation, but that direct-current power supply would become increasingly important for subsequent generations
  • The Gunsan AI Data Center that kt cloud is developing with SGC Energy is planned to expand from 60MW in Phase 1 to a maximum of 300MW, and will use modular and skid solutions and a liquid-cooling design that supports Vera Rubin on every floor
  • Depending on project conditions, modular construction is expected to reduce the existing construction period of 3~4 years to around 14~16 months. kt cloud is preparing design standards and a commissioning framework to expand its supply of 1GW-scale AI data centers by 2031